Question: Problem 14-2 (Algo) Using the BOM shown below, What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.)
Problem 14-2 (Algo)
Using the BOM shown below,
What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.)