Question: Based on the Cost Variance ( CV ) , which tasks are over - budget as of the status date of 3 / 3 1
Based on the Cost Variance CV which tasks are overbudget as of the status date of
Question options:
Need survey
Set product specs
Shelf life report
Nutrition report
Select fruit suppliers
Equipment rehab
Market testing