Question: Based on the following factitious activity table for the project schedule. In the activity table below, all duration estimates are in weeks, and the network
Based on the following factitious activity table for the project schedule.
In the activity table below, all duration estimates are in weeks, and the network proceeds from Node 1 to Node 8.
| Activity | Initial Node | Final Node | Estimated Duration |
| A | 1 | 2 | 10 |
| B | 1 | 3 | 12 |
| C | 1 | 4 | 8 |
| D | 2 | 3 | 4 |
| E | 2 | 5 | 8 |
| F | 3 | 4 | 6 |
| G | 4 | 5 | 4 |
| H | 4 | 6 | 8 |
| I | 5 | 6 | 6 |
| J | 5 | 8 | 12 |
| K | 6 | 7 | 8 |
| L | 7 | 8 | 10 |
Questions
- Find the critical path for this project and determine how long it is. Show your steps to justify your answer.
(2 mark)
Ans.
- Based on the information above, in case there is any resource conflict happened. Explain your approach to resolve the conflict.
(3 mark)