Question: Based on the following factitious activity table for the project schedule. In the activity table below, all duration estimates are in weeks, and the network

Based on the following factitious activity table for the project schedule.

In the activity table below, all duration estimates are in weeks, and the network proceeds from Node 1 to Node 8.

Activity

Initial Node

Final Node

Estimated Duration

A

1

2

10

B

1

3

12

C

1

4

8

D

2

3

4

E

2

5

8

F

3

4

6

G

4

5

4

H

4

6

8

I

5

6

6

J

5

8

12

K

6

7

8

L

7

8

10

Questions

  1. Find the critical path for this project and determine how long it is. Show your steps to justify your answer.

(2 mark)

Ans.

  1. Based on the information above, in case there is any resource conflict happened. Explain your approach to resolve the conflict.

(3 mark)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!