Question: Based on the following table, create a project network diagram. From the project network diagram, make a Gantt chart. Activity / Predecessor / Duration A
Based on the following table, create a project network diagram. From the project network diagram, make a Gantt chart.
Activity / Predecessor / Duration
A / - / 4
B / - / 5
C / A / 5
D / A / 6
E / B, C / 5
F / D / 4
G / E / 5