Question: Based on the following table, create a project network diagram. From the project network diagram, make a Gantt chart. Activity / Predecessor / Duration A

Based on the following table, create a project network diagram. From the project network diagram, make a Gantt chart.

Activity / Predecessor / Duration

A / - / 4

B / - / 5

C / A / 5

D / A / 6

E / B, C / 5

F / D / 4

G / E / 5