Question: Based on the following table, make a project network diagram. Activity / Predecessor / Duration A / - / 4 B / - / 5
Based on the following table, make a project network diagram.
Activity / Predecessor / Duration
A / - / 4
B / - / 5
C / A / 5
D / A / 6
E / B, C / 5
F / D / 4
G / E / 5
Include for each activity:
Early Start (ES)
Early Finish (EF)
Late Start (LS)
Late Finish (LF)
Step by Step Solution
There are 3 Steps involved in it