| A | B | C | D |
| Budgeted | 60,000 | 120,000 | 50,000 | 60,000 |
| Planned | 80% | 65% | 40% | 30% |
| Performed | 88% | 50% | 50% | 5% |
| Actual Costs | 55,000 | 80,000 | 30,000 | 30,000 |
| Metric | Formula | Result | Meaning |
| BAC | - |
|
|
| EV | % performed x budget |
|
|
| PV | % planned x budget |
|
|
| AC | Non applicable |
|
|
| CV | EV AC |
|
|
| SV | EV PV |
|
|
| CPI | EV / AC |
|
|
| SPI | EV / PV |
|
|
| EAC | BAC / CPI |
|
|
| VAC | BAC - EAC |
|
|