Question: Based on the following table, please create a diagram. Also please calculate and show the ES, EF, LS, LF times along with the slack for
Based on the following table, please create a diagram. Also please calculate and show the ES, EF, LS, LF times along with the slack for each activity using the critical path methodology.
Required completion is 30 weeks.
| Activity | Estimated Time (Weeks) | Actual Finish Time (Weeks) | Immediate Predecessor |
| A | 6 | 6 | |
| B | 5 | 8 | |
| C | 7 | 11 | a |
| D | 9 | 9 | A |
| E | 4 | C,D | |
| F | 5 | B,D | |
| G | 3 | B | |
| H | 10 | E,F,G |
Based on your completed network diagram please answer the following questions.
- What is the critical path for the project at the end of the planning process?
- At the end of the planning process, can the project meet its required completion date? What is its estimated completion date?
- Before applying the actual finish times, which activities pose the greatest risk to the project and why?
- After applying the actual finish time, identify the activity(s) that should be concentrating on to get the project back on schedule?
- What tools would you use to bring it back on schedule once you apply the actuals?