Question: Based on the following table, we'd like to create AON network. What's the critical path? Activity Predecessor Duration (days) A 3 B A 4 C

Based on the following table, we'd like to create AON network. What's the critical path?

Activity

Predecessor

Duration (days)

A

3

B

A

4

C

A

2

D

B

5

E

C

1

F

C

2

G

D, E

4

H

F, G

3

a.

A->B->D->G->H

b.

A->C->E->G->H

c.

A->C->F->H

d.

A->B->E->G->H