Question: Consider a project with 10 activities, which are described in the table below. Given the activity information, draw a network diagram and complete all network
- Consider a project with 10 activities, which are described in the table below. Given the activity information, draw a network diagram and complete all network calculations using the AON method. Identify the project duration and the critical path.
| Activity | Predecessor | Duration (Days) |
| A | None | 10 |
| B | None | 14 |
| C | None | 14 |
| D | A,B,C,D | 29 |
| E | A,B,C,D | 26 |
| F | D,E | 51 |
| G | F | 19 |
| H | F | 19 |
| I | F | 8 |
| J | G,H,I | 4 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
