Question: Consider a project with 10 activities, which are described in the table below. Given the activity information, draw a network diagram and complete all network

  1. Consider a project with 10 activities, which are described in the table below. Given the activity information, draw a network diagram and complete all network calculations using the AON method. Identify the project duration and the critical path.

Activity

Predecessor

Duration (Days)

A

None

10

B

None

14

C

None

14

D

A,B,C,D

29

E

A,B,C,D

26

F

D,E

51

G

F

19

H

F

19

I

F

8

J

G,H,I

4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!