Question: Based on the given data table below, how many days can the project be reduced by after applying all possible crashing steps? a. 5 days

Based on the given data table below, how many days can the project be reduced by after applying all possible crashing steps?

Based on the given data table below, how many

a.

5 days

b.

4 days

c.

6 days

d.

3 days

e.

7 days

Precedence Duration, Days (normal, crash) Activity a b 3,2 a Cost (normal, craslo) $ 40, 80 20, 80 20,20 30,120 10, 80 2,1 2,2 4,1 3,1 a b Table 9-1 d, partial crashing allowed e, partial crashing not allowed