Question: Based on the given data table below, how many days can the project be reduced by after applying all possible crashing steps? a. 5 days
Based on the given data table below, how many days can the project be reduced by after applying all possible crashing steps?

a.
5 days
b.
4 days
c.
6 days
d.
3 days
e.
7 days
Precedence Duration, Days (normal, crash) Activity a b 3,2 a Cost (normal, craslo) $ 40, 80 20, 80 20,20 30,120 10, 80 2,1 2,2 4,1 3,1 a b Table 9-1 d, partial crashing allowed e, partial crashing not allowedStep by Step Solution