Question: Based on the given information below related to a project, calculate Earned Value ( EV ) . Project duration: 4 months Project budget ( BAC

Based on the given information below related to a project, calculate Earned Value (EV).
Project duration: 4 months
Project budget (BAC): $10,000
Elapsed time: 3 months
% Complete (planned): 75%
% Complete (actual): 50%
Current Actual Cost: $5,500