Question: Based on the information given in the table above, draw the Network diagram using the Arrow Diagramming Method (ADM). Based on the information given in
Based on the information given in the table above, draw the Network diagram using the Arrow Diagramming Method (ADM).
Based on the information given in the table above, draw the Network diagram using the Arrow Diagramming Method (ADM). [4 marks]. Activity Predecessor Duration (day) 1 B 3 A 4 D B 3 E CD 5 F D 4 G E 5 H D 3 I G 4 J HEI 3