Question: Activity Predecessor Duration (day) A B 3 A 4 D B 3 E C.D 5 F D G E 5 H D 3 1 G

Activity Predecessor Duration (day) A B 3 A 4 D B
Activity Predecessor Duration (day) A B 3 A 4 D B 3 E C.D 5 F D G E 5 H D 3 1 G 4 J H.FI 3 Question 1 Based on the information given in the table above, draw the Network diagram using the Arrow Diagramming Method (ADM). [4 marks) Question 2 Find all possible paths with their total durations. [3 marks] Question 3 Specify the critical path. [1 mark] Question 4 What is the earliest time to complete the project? [1 mark]