Question: Based on the information given in the Table below, create the project schedule, find the start/finish for each task, find the total duration, determine the
Based on the information given in the Table below, create the project schedule, find the start/finish for each task, find the total duration, determine the critical path. Answer the questions based on your work. Normal Crashed Duration Activity Predecessor Duration Cost to crash (per day) (days) (days) none 6 150 KD 250 KD A 2 170 KD A 3 75 KD - I - WONNA B, C 7 175 KD 4 50 KD CD E, F G O KD 100 KD For additional help refer to the Operations Management Textbook Operations Management Textbook (Critical Path p. 578-582, Crashing p. 591-594). Draw the diagram correctly, include the early start, early finish, late start, late finish, and slack for each of the task. Finally determine the critical path. Once completed, upload your work below (you do not need to type anything in the textbox) and use your map to answer the following questions. A B 1 E E 1 8 c? Maximum file size: 10MB, maximum number of files: 1 + Files Accepted file types Presentation files des non nin Name: Use the objects below to create the project schedule, and fill in the start/finish value and slack for each task. Finally, identify the critical path. Once finished, save and upload this file into the Homework. Slack ES EF LS LF Slack ES EF LS LF Slack ESEF LS LF Slack ESEF LS LF Slack ESEF LS LF Slack ESEF LS LF Slack ESEF LS LF Slack ES EF LS LF 6 B 5 2 D 3 F 7 E 4 G 3 NI What is the critical path? a. A-B-E-G-H O b. C-D-F OC.A-C-F-G-H d. A-C-E-G-H O e. A-B-C-D Of. A-D-F-G-H O g. A-B-C-D-E-F-G-H What is the project's duration? a. 11 days b. 21 days c. 8 days d. 19 days O e. 15 days f. 23 days g. 32 days h. 25 days What is the slack time for activity D? a. O b. 5 O c. 1 O d. 2 O e.3 What is the slack time for activity E? a. 3 O b.5 Oc. O d. 7 e. 11 What is the late finish time for activity C? a. Day 14 b. Day 8 O c. Day 3 d. Day 6 e. Day 8 Of. Day 11 If task C gets delayed by 2 days, what will happen to project completion time? a. Completion gets delayed by 1 day b. Completion time finishes early by 2 days c. Completion gets delayed by 5 days d. Nothing. Project completion time stays the same e. Completion gets delayed by 2 days If task F gets delayed by 5 days, what happens to project completion time? a. Completion time gets delayed by 11 days b. Completion time gets delayed by 2 days c. Nothing. Project Completion time stays the same. d. Completion time gets delayed by 3 days e. Completion time gets delayed by 5 days If task F finishes faster by 1 day, what will happen to the project completion time? a. Project completion time be faster by 1 day b. Project completion time will get be faster by 5 days c. Nothing. Project completion will stay the same d. Project completion will get delayed by 1 day e. Project completion time will be delayed by 3 days If I want to crash the project by 1 day. Which would be the cheapest task to crash to achieve this? a.D ob. . d. A e. f.G If my client will pay me a bonus of 600 KWD if I can deliver the project early by 3 days. How much can I profit? (Take the bonus of 600 KWD minus the least cost to crash 3 days) a. 600 KWD b. 200 KWD c. 150 KWD d. 550 KWD e.325 KWD f. 400 KWD g. 100 KWD h. 800 KWD 1.300 KWD j. The cost to crash 3 days is more than the bonus