Question: Based on the information provided, assess and document your opinion about the realism of the EAC for the A - 1 2 program. To help

Based on the information provided, assess and document your opinion about
the realism of the EAC for the A-12 program.
To help you with the assessment, answer the following questions:
What percent complete is the project? [EV/BAC][Answer: ]
What percent was scheduled to be complete? [PV/BAC][Answer: ]
What percent has been spent of the EAC? [AC/EAC][Answer: ]
Compare CPI and TCPI for realism:
CPI shows the cost efficiency to date [Answer: ]
TCPI shows the required cost efficiency to meet the EAC [Answer: ]
If the CPI and TCPI are more than 10% different, the EAC is very likely to be unrealistic [(TCPI-CPI)/CPI]
X 100[Answer: ]
Compare the overrun to date (CV) with the overrun at the end of the project (VAC):
The CV shows the cost variance to date [CV = EV AC][Answer: ]
The VAC shows the projected cost variance at the end of the project, based on the EAC [VAC = BAC
EAC][Answer: ]
If the overrun to date (CV) is worse than the projected final overrun (VAC), then a recovery is NOT
expected; recoveries of more than 10% are rare, especially if the project is more than 20% complete
[VAC-CV)/CV] X 100 and EV/BAC X 100[Answer: ]
Calculate two statistical EACs, based on trends to date:
Low End Statistical EAC (1)= AC +[(BAC EV)/ CPI][Answer: ]
High End Statistical EAC (2)= AC +[(BAC EV)/(CPI X SPI)][Answer: ]
If you were a consultant for the government, what action would you
recommend for the A-12 Program? [Answer: ]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!