Question: Based on the information provided, what are the current Planned Releases for Product A for weeks 11-18. Enter these into cells C16-J16 on the MRP

Based on the information provided, what are theBased on the information provided, what are theBased on the information provided, what are theBased on the information provided, what are the

Based on the information provided, what are the current Planned Releases for Product A for weeks 11-18. Enter these into cells C16-J16 on the MRP Problem tab of your workbook.

In addition to filling in the complete row in the Excel spreadsheet, enter the two values requested below:

Planned Releases for Item A in week 11:

Planned Releases for Item A in week 12:

Based on the information provided, what are the current Gross Requirements for Item D for weeks 11-18. Enter these into cells C32-J32 on the MRP Problem tab of your workbook.

In addition to filling in the complete row in the Excel spreadsheet, enter the two values requested below:

Item D Gross Requirements for Week 11:

Item D Gross Requirements for Week 12 :

Based on the information provided, what are the current Gross Requirements for Item E for weeks 11-18. Enter these into cells C36-J36 on the MRP Problem tab of your workbook.

In addition to filling in the complete row in the Excel spreadsheet, enter the two values requested below:

Item E Gross Requirements for Week 11 :

Item E Gross Requirements for Week 12 :

Based on the information provided, what will we be seeing next week in the Scheduled Receipt row, when we come back and complete the Item C MRP table covering weeks 12-19. Enter these into the cells N16-U16 on the MRP Problem tab of your workbook.

In addition to filling in the complete row in the Excel spreadsheet, enter the two values requested below:

Item C Scheduled Receipts for week 12, in the week 12-19 MRP table:

Item C Scheduled Receipts for week 13, in the week 12-19 MRP table:

*I entered what I though the answers were... may be wrong though*

IVI D (3) A 1 PRODUCT STRUCTURE TREE 2 3 A 4 5 6 B (2) C (5) 7 8 9 E (2) 10 11 12 13 14 ITEM A 15 Week: 11 12 13 14 Planned 24 26 26 29 16 Release 17 18 19 ITEMC 20 On Hand: 165 Lead Time: 3 Weeks 21 Safety Stock: 50 Lotsize: POQ = 2 Weeks 22 Week 11 12 13 14 Student Information MRP Problem Project Scheduling Problem Queuing Problem Ready F (4) 15 16 17 18 ITEM C SCHEDULED RECE Week: Planned Release 25 27 26 0 ITEM B On Hand: Safety Stock: Week 110 50 15 16 - Single Server Madel 17 18 Multiple Servers Model Average: 107.5 Count: 13 Sum: 1075 200% A B D E H M Lead Time: 3 Weeks Lotsize: POQ = 2 Weeks 12 13 110 50 14 15 16 17 18 130 130 145 125 135 130 275 ITEM B On Hand: Safety Stock: Week: Gross Requirements Scheduled Receipts Projected On Hand Net Requirement Planned Receipt Planned Release 190 60 175 50 180 50 50 18 19 ITEM C 20 On Hand: 165 21 Safety Stock: 50 22 Week: 11 Gross 120 23 Requirements Scheduled 24 Receipts Projected 165 45 25 On Hand Net 5 26 Requirement Planned 27 Receipt Planned 260 28 Release 29 30 ITEM D GROSS REQUIREMENTS 31 Week: 11 Gross 780 110 135 135 260 265 265 12 13 14 15 16 17 18 n 795 0 Picture 1 Xfx D E F G . T J M 260 265 L Requirement Planned Receipt Planned Release 265 12 13 14 15 16 17 18 A B C 26 Requirement Planned 27 Receipt Planned 260 28 Release 29 30 ITEM D GROSS REQUIREMENTS 31 Week: 11 Gross 32 Requirements 780 33 34 ITEM E GROSS REQUIREMENTS 35 Week: 11 Gross 520 36 Requirements 37 38 0 795 0 0 0 0 0 12 13 14 15 16 17 18 0 530 0 0 0 0 0 | J K L M N 0 P Q R S T. U V W 12 13 14 15 17 18 14 15 16 17 18 19 ITEM C SCHEDULED RECEIPTS NEXT WEEK Week: 12 13 Planned Release 26 0 16 17 18 19 20 21 22 110 50 Lead Time: 2 Weeks Lotsize: FOQ = 150 12 13 17 18 11 14 15 16 17 18 130 48 52 52 58 50 54 52 23 150 24 ITEM B On Hand: Safety Stock: Week: Gross Requirements Scheduled Receipts Projected On Hand Net Requirement Planned Receipt Planned Release 50 50 110 25 26 27 28 20 IVI D (3) A 1 PRODUCT STRUCTURE TREE 2 3 A 4 5 6 B (2) C (5) 7 8 9 E (2) 10 11 12 13 14 ITEM A 15 Week: 11 12 13 14 Planned 24 26 26 29 16 Release 17 18 19 ITEMC 20 On Hand: 165 Lead Time: 3 Weeks 21 Safety Stock: 50 Lotsize: POQ = 2 Weeks 22 Week 11 12 13 14 Student Information MRP Problem Project Scheduling Problem Queuing Problem Ready F (4) 15 16 17 18 ITEM C SCHEDULED RECE Week: Planned Release 25 27 26 0 ITEM B On Hand: Safety Stock: Week 110 50 15 16 - Single Server Madel 17 18 Multiple Servers Model Average: 107.5 Count: 13 Sum: 1075 200% A B D E H M Lead Time: 3 Weeks Lotsize: POQ = 2 Weeks 12 13 110 50 14 15 16 17 18 130 130 145 125 135 130 275 ITEM B On Hand: Safety Stock: Week: Gross Requirements Scheduled Receipts Projected On Hand Net Requirement Planned Receipt Planned Release 190 60 175 50 180 50 50 18 19 ITEM C 20 On Hand: 165 21 Safety Stock: 50 22 Week: 11 Gross 120 23 Requirements Scheduled 24 Receipts Projected 165 45 25 On Hand Net 5 26 Requirement Planned 27 Receipt Planned 260 28 Release 29 30 ITEM D GROSS REQUIREMENTS 31 Week: 11 Gross 780 110 135 135 260 265 265 12 13 14 15 16 17 18 n 795 0 Picture 1 Xfx D E F G . T J M 260 265 L Requirement Planned Receipt Planned Release 265 12 13 14 15 16 17 18 A B C 26 Requirement Planned 27 Receipt Planned 260 28 Release 29 30 ITEM D GROSS REQUIREMENTS 31 Week: 11 Gross 32 Requirements 780 33 34 ITEM E GROSS REQUIREMENTS 35 Week: 11 Gross 520 36 Requirements 37 38 0 795 0 0 0 0 0 12 13 14 15 16 17 18 0 530 0 0 0 0 0 | J K L M N 0 P Q R S T. U V W 12 13 14 15 17 18 14 15 16 17 18 19 ITEM C SCHEDULED RECEIPTS NEXT WEEK Week: 12 13 Planned Release 26 0 16 17 18 19 20 21 22 110 50 Lead Time: 2 Weeks Lotsize: FOQ = 150 12 13 17 18 11 14 15 16 17 18 130 48 52 52 58 50 54 52 23 150 24 ITEM B On Hand: Safety Stock: Week: Gross Requirements Scheduled Receipts Projected On Hand Net Requirement Planned Receipt Planned Release 50 50 110 25 26 27 28 20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!