Question: Based on the information provided, what is the planned release of product A in week 11-18? Enter this information in the cells below. PRODUCT STRUCTURE


Based on the information provided, what is the planned release of product A in week 11-18? Enter this information in the cells below. 

PRODUCT STRUCTURE TREE A B (2) C (5) D (3) E (2) F (4) 160 50 Lead Time: 3 Weeks Lotsize: POQ = 2 Weeks 12 13 14 11 15 16 17 18 115 140 100 120 100 135 135 275 ITEM C On Hand: Safety Stock Week: Gross Requirements Scheduled Receipts Projected On Hand Net Requirement Planned Receipt Planned Release 160 45 180 80 150 50 185 50 50 5 90 135 190 270 190 270 11 12 13 14 15 16 17 18 4 ITEM A 5 Week: Planned 6 Release 7 In addition to filling in the complete row in the Excel spreadsheet, enter the two values requested below: Planned Releases for Item A in week 11: Planned Releases for Item A in week 12
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts