Question: Based on the late start date, what is the time phased cumulative budget at the end of period 10. Show calculation You have a project
Based on the late start date, what is the time phased cumulative budget at the end of period 10. Show calculation

You have a project with the following activities. Based on the LS dates, what is the time- phased cumulative budget at the end of period 107 Show your calculations. Activity Duration Producessors Expected Cost 10,000 15 0709 10 DOO 2 20.000 15 000 4.5 20.DO0 20/900 719 20.000