Question: You have a project with the following activities. Based on the LF dates, what is the time- phased cumulative budget at the end of period

You have a project with the following activities. Based on the LF dates, what is the time- phased cumulative budget at the end of period 10? Show your calculations. Activity Duration Predecessors Expected Cost 6 6.000 4 4.000 6,000 1,2 1,000 3.4 1.000 CO OO NO) UI A W N 4 5,000 4,5,6 8,000 7,10 5,000 10 6 10,000 10 25 7,9 25,000 No calculations, no marks You can use the HTML Editor to enter your answer in tables. You can also insert images and files