Question: Based on the network below, what is the late start (LS) of B if the duration (t) of A is 16 days, B is 8

Based on the network below, what is the late
Based on the network below, what is the late start (LS) of B if the duration (t) of A is 16 days, B is 8 days, C is 10 days, and Dis 12 days? (2 Points) A D B 16 0 24 0 0 18 26 cannot be determined from the information provided Based on the network below, what is the late start (LS) of B if the duration (t) of A is 16 days, B is 8 days, C is 10 days, and Dis 12 days? (2 Points) A D B 16 0 24 0 0 18 26 cannot be determined from the information provided