Question: A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In

A construction company has a project proposal, which takes 10 activities as follows:

Activity

Predecessors

Activity Duration Time

(In DAYS )

Early Start (ES)

(In DAYS )

Early Finish

(EF)

(In DAYS )

Late Start (LS)

(In DAYS )

Late Finish

(LF)

(In DAYS )

SLACK

(In DAYS )

A

-

14

B

-

13

C

A

11

D

A

15

E

B

14

F

B

11

G

D, E

13

H

F

15

J

C

12

K

G,H

11

  1. Complete the table. (11 pts)
  2. What is the critical path? ( 5 pts)
  3. Based on critical path, what is the expected time in days to complete this project? ( 5 pts)
  4. Is it possible to delay activity-B without delaying the project? ( 1 pts)
  5. If yes, then how many days can activity-B be delayed without delaying the project?

If No, then list at least one activity which can be delayed without delaying the project. ( 1 pts)

  1. Is it possible to delay activity-G without delaying the project? ( 1 pts)
  2. If yes, then how many days can activity-G be delayed without delaying the project?

If No, then list at least one activity which can be delayed without delaying the project. ( 1 pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!