Question: A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In
A construction company has a project proposal, which takes 10 activities as follows:
| Activity | Predecessors | Activity Duration Time (In DAYS ) | Early Start (ES) (In DAYS ) | Early Finish (EF) (In DAYS ) | Late Start (LS) (In DAYS ) | Late Finish (LF) (In DAYS ) | SLACK (In DAYS ) |
| A | - | 14 | |||||
| B | - | 13 | |||||
| C | A | 11 | |||||
| D | A | 15 | |||||
| E | B | 14 | |||||
| F | B | 11 | |||||
| G | D, E | 13 | |||||
| H | F | 15 | |||||
| J | C | 12 | |||||
| K | G,H | 11 |
- Complete the table. (11 pts)
- What is the critical path? ( 5 pts)
- Based on critical path, what is the expected time in days to complete this project? ( 5 pts)
- Is it possible to delay activity-B without delaying the project? ( 1 pts)
- If yes, then how many days can activity-B be delayed without delaying the project?
If No, then list at least one activity which can be delayed without delaying the project. ( 1 pts)
- Is it possible to delay activity-G without delaying the project? ( 1 pts)
- If yes, then how many days can activity-G be delayed without delaying the project?
If No, then list at least one activity which can be delayed without delaying the project. ( 1 pts)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts