Question: Based on the network diagram and associated cost table below, complete the time phased budget. Please create the time-phased budget table and insert it to
Based on the network diagram and associated cost table below, complete the time phased budget. Please create the time-phased budget table and insert it to the answer field. It should include Total and Cumulative amounts.
| Task | Cost |
| A | 5, 5 |
| B | 10 |
| C | 8, 1, 8 |
| D | 4 |
| E | 5, 5 |
| F | 2, 2, 2 |
| G | 3, 3 |
| H | 5, 2 |
Step by Step Solution