Question: Based on the Plan information given in the sketch below; Create a set of Level Notes by calculating the Elevations at the various Grid Points
Based on the Plan information given in the sketch below;
Create a set of Level Notes by calculating the Elevations at the various Grid Points based on Grid Foresights shown.
Beginning Benchmark # value USC&G Datum
The Backsight value calculate the HI and the various Grid Elevations. Stationing should be labeled as A A etc.
If the Foresight Reading on Benchmark # but the True Elevation Value of Benchmark # what is the Vertical Error of Closure.
Use Example of Differential Leveling Notes.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock