Question: Based on the Plan information given in the sketch below; Create a set of Level Notes by calculating the Elevations at the various Grid Points

Based on the Plan information given in the sketch below;
Create a set of Level Notes by calculating the Elevations at the various Grid Points based on Grid Foresights shown.
Beginning Benchmark #5 value =+73.60' USC&G Datum
The Backsight value =+5.25 calculate the HI and the various Grid Elevations. Stationing should be labeled as A 1, A 2, etc.
If the Foresight Reading on Benchmark #10=-3.23, but the True Elevation Value of Benchmark #10=75.58 what is the Vertical Error of Closure.
Use 5-1c Example of Differential Leveling Notes.
Based on the Plan information given in the sketch

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!