Question: Based on the table below: b . Conduct both a forward and backward pass using AON notation. What is the e Activity Predecessors Duration (

Based on the table below:
b. Conduct both a forward and backward pass using AON notation. What is the e
Activity Predecessors Duration (Days)
A None 4
B A (FS2)4
C A (SS)2
D A 6
E C (SS1)2
F B 4
G E (FF1)2
H E, F 2
I D 3
J G, H, I 4