Question: Based on the table below, perform resource-limited scheduling. Activity A is the project start activity and activity E is the closure activity. Assume that each

Based on the table below, perform resource-limited scheduling. Activity A is the project start activity and activity E is the closure activity. Assume that each of the other tasks may be performed independently or concurrently with the other tasks except task B which has a latest start time of day 9.No task may be interrupted once started. Also, assume that only two workers are available at any given time and no workers may be idle for a day or more.Draw a resource levelled Gantt chart and clearly indicate the new completion time for the project?