Question: Based on the Time Chart I Project A, as shown in Table 1, assuming that the project team will work a standard working week (5

Based on the Time Chart I Project A, as shown in

Based on the Time Chart I Project A, as shown in Table 1, assuming that the project team will work a standard working week (5 working days in a week) and all tasks will start as soon as possible. Table 1: Time Chart I Project A Activity Description Preceded by Time (days) To apply for approval none 5 B Installation of foundation A 10 Fabricate steel elements 10 D Fabricate tower elements 20 E Fabricate steel ropes A 15 F A 10 Fabricate supporting elements Transport all item from plant to site G C,D,E,F 5 H Erection of the suspension bridge B.G 10 | Fine-tuning . 5 J Testing 5 (a) Construct a network logic diagram using the Precedence Diagramming Method (AON: Activity-On-Node format). (5 marks, C3) (b) Construct a network logic diagram using the Arrow Diagramming Method (AOA: Activity-On-Arrow format). (5 marks, C3) (C) Using the answer from 3(b) - AOA format i. ii. Determine all the possible path activities. Determine the critical path activities and duration Calculate the planned duration of the project in weeks. (5 marks, C3) (2 marks, C3) (3 marks, C3)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!