Question: Based on this table, what is the project completion time? Based on this table, what is the project completion time? A) 10 days B) 15

 Based on this table, what is the project completion time? Based

Based on this table, what is the project completion time?

Based on this table, what is the project completion time?

A) 10 days

B) 15 days

C) 23 days

D) 27 days

Based on Table in Question 4, what is the critical path?

A) Start - A-B-C-E-F- finish

B) Start -A-E-F - finish

C) Start -A -B-D-F- finish

D) Start- B-D-F- finish

\begin{tabular}{|c|c|} \hline Activity & EstimatedDuration(TE) \\ \hline A-B & 6 \\ \hline B-C & 7 \\ \hline B-D & 6 \\ \hline C-E & 9 \\ \hline E-F & 5 \\ \hline D-F & 11 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!