Question: Based on your project schedule, you should have completed 2 major deliverables by now. However, when you checked your schedule, you realized that you will


Based on your project schedule, you should have completed 2 major deliverables by now. However, when you checked your schedule, you realized that you will be late. So, you decide that the schedule can be met by adding additional developers to the activities on the critical path. This is an example of: O A. Resource leveling O B. Fast tracking O C. Crashing O D. Scope creep