Question: Based on your project, you have access to the CPI and EV for the project, but not the AC . The CPI is 0 .

Based on your project, you have access to the CPI and EV for the project, but not the AC. The CPI is 0.92, and the EV is $172,500. How much money has actually been spent on the project?