Question: Based solely o n the critical path, estimate the probability that the project will b e completed within 1 0 weeks. I f required, round

Based solely on the critical path, estimate the probability that the project will be completed within 10 weeks.
If required, round your answers to two decimal places. Enter 0if your answer is zero.
ActivityExpected Time (in Weeks)VarianceAfillin the blank 2fill in the blank 3Bfill in the blank 4fill in the blank 5Cfill in the blank 6fill in the blank 7
fill in the blank 8.
z= fill in the blank 9.
Cumulative probability = fill in the blank 10.
Using all paths through project network, estimate the probability that the project will be complete within 10 weeks.
ABCA-BA-CB-CA-B-CB-A-CA-C
Expected time = fill in the blank 12 weeks. If required, round your answers to two decimal places.
fill in the blank 13.If required, round your answers to two decimal places.
z= fill in the blank 14.If required, round your answers to two decimal places.
Cumulative probability = fill in the blank 15.If required, round your answers to two decimal places.
P(entire project completed)= fill in the blank 16.If required, round your answers to three decimal places.
Should you use the estimate in(b)or(c)?
Use the estimate in(b).Use the estimate in(c).Use the estimate in(c).
Feedback Area
Feedback
Partially correct GIVE ME CORRECT ANSWER
Problem 9-16 report for management on a daily basis.
??Immediate?Time(weeks)?ActivityDescriptionPredecessor(s)OptimisticMostProbablePessimisticAReportgeneration-1711BWebscraping-3810CTestingAB111
a. Choose the project network.
(i)
(ii)
(iii)
(iv)
b. Based solely on the critical path, estimate the probability that the project will be completed within 10 weeks.
If required, round your answers to two decimal places. Enter "0"if your answer is zero.
c. Using all paths through project network, estimate the probability that the project will be complete within 10 weeks.
Expected time = weeks. If required, round your answers totw
2=.If required, round your answers to two decimal places.
z=.If required, round your answers to two decimal places.
weeks. If required, round your answers to two decimal places.
Cumulative probability =
.If required, round your answers to two decimal places.
entire project completed
Based solely o n the critical path, estimate the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!