Question: Problem 9 - 1 6 report for management o n a daily basis. ? b egin { t a b u l a r }

Problem 9-16 report for management on a daily basis.?b
egin{tabular}{clcccc}
& & Immediate & & lticolumn{2}{c}{ Time (weeks)}???
Activity & Description & Predecessor(s) & Optimistic & Most Probable & Pessimistic???
?hlineA & Report generation & - & 1 & 7 & 11???
B & Web scraping & - & 3 & 8 & 10???
C & Testing & A,B & 1 & 1 & 1?e
nd{tabular}
a. Choose the project network.
(i)
(ii)
(iii)
(iv)
b. Based solely on the critical path, estimate the probability that the project will be completed within 10 weeks.
If required, round your answers to two decimal places. Enter "0"if your answer is zero.
c. Using all paths through project network, estimate the probability that the project will be complete within 10 weeks.
Expected time = weeks. If required, round your answers totw
2=.If required, round your answers to two decimal places.
z=.If required, round your answers to two decimal places.
weeks. If required, round your answers to two decimal places.
Cumulative probability =
.If required, round your answers to two decimal places.
entire project completed
Problem 9 - 1 6 report for management o n a daily

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!