Question: Based upon the following data, develop your recommended allocation of work and the number of work stations. Minimum required production per day is 160
Based upon the following data, develop your recommended allocation of work and the number of work stations. Minimum required production per day is 160 units in 8 hours shift. Calculate the required number of operators and work stations, position weight and unassigned time. 8 (1)- (2)- (5). -(7) (3) (4)- (8) (9) Work element 1 2 3 4 5 6 7 8 9 10 (6)- (10) Work Time /Unit, H 0.0333 0.0167 0.0117 0.0167 0.0260 0.0168 0.0200 0.0067 0.0333 0.0017 071 3min
Step by Step Solution
3.31 Rating (148 Votes )
There are 3 Steps involved in it
Let us first graphically see how much maximum time is taken in completing the process 1 00333 3 00117 8 00067 10 00017 Here 1257 is the longest sequen... View full answer