Question: Based upon the following data, develop your recommended allocation of work and the number of work stations. Work Unit Estimated Work Unit Time in Minutes
Based upon the following data, develop your recommended allocation of work and the number of work stations.

Work Unit Estimated Work Unit Time in Minutes 0.76 1.24 2 0.84 3 2.07 1.47 2.40 0.62 2.16 4.75 0.65 10 1.45 (0)(3)-(4)(5)(6)-(9)+(10) (1)(2)+(7)(8)
Step by Step Solution
3.55 Rating (172 Votes )
There are 3 Steps involved in it
Minimum required production per day is 90 assemblies A precedence matrix as follows was developed by ... View full answer