Question: BE 6 - 1 2 Performance obligations; construction LO 6 - 5 On January 1 , 2 0 2 4 , Lego Construction Company signed
BE Performance obligations; construction LO On January Lego Construction Company signed a contract to build a custom garage for a customer and received $ in advance for the job. The new garage will be built on the customer's land. To complete this project, Lego must first build a concrete floor, construct wooden pillars and walls, and finally install a roof. Lego normally charges standalone prices of $ $ and $ respectively, for each of these three smaller tasks if done separately. How many performance obligations exist in this contract?