Question: be Each time the schedule is recalculated in the project, the schedule a. examined for a change in critical paths then fast track the new

be Each time the schedule is recalculated in the
be Each time the schedule is recalculated in the project, the schedule a. examined for a change in critical paths then fast track the new critical path O b. accelerated on all paths with a positive slack. C. analyzed to see if it needs further adjustment d. examined and assign additional resources to the activities with free slack