Question: Before starting project execution, the project manager obtained final sign-off on the baselines for scope, schedule, and cost and for the other plan documents. What
Before starting project execution, the project manager obtained final sign-off on the baselines for scope, schedule, and cost and for the other plan documents. What life cycle was being used by the project manager and the team