Question: Beginning Workers 100 Beginning inventory = 2000 Productive hours/worker/day = 6.75 Units per worker per month 100 Chase Strategy Jan Feb Mar Apr May June
| Beginning Workers | 100 | |
| Beginning inventory = | 2000 | |
| Productive hours/worker/day = | 6.75 | |
| Units per worker per month | 100 | |
| Chase Strategy | Jan | Feb | Mar | Apr | May | June |
| Demand | 15,200 | 14,250 | 7,000 | 10,300 | 13,650 | 17,000 |
| Beginning Inv. | ||||||
| Net Requirements | ||||||
| Beginning Workers | ||||||
| Hired | ||||||
| Fired | ||||||
| Req. Workers | ||||||
| Production | ||||||
| Ending Inventory |
Using the chase strategy what is the net requirement in June?
Group of answer choices
17,050 units
17,000 units
13,600 units
16,000 units