Question: Beginning Workers 100 Beginning inventory = 2000 Productive hours/worker/day = 6.75 Units per worker per month 600 Chase Strategy Jan Feb Mar Apr May June
| Beginning Workers | 100 | ||
| Beginning inventory = | 2000 | ||
| Productive hours/worker/day = | 6.75 | ||
| Units per worker per month | 600 | ||
| Chase Strategy | Jan | Feb | Mar | Apr | May | June |
| Demand | 145,000 | 127,000 | 89,000 | 110,000 | 133,000 | 162,000 |
| Beginning Inv. | ||||||
| Net Requirements | ||||||
| Beginning Workers | ||||||
| Hired | ||||||
| Fired | ||||||
| Req. Workers | ||||||
| Production | ||||||
| Ending Inventory |
Using the chase strategy, what is the number of required workers for April?
Group of answer choices
103
212
183
222