Question: begin{tabular}{ccc} hline Activity & Duration (days) & Predecessors hline A & 7.5 & None B & 6 & None C & 7


\begin{tabular}{ccc} \hline Activity & Duration (days) & Predecessors \\ \hline A & 7.5 & None \\ B & 6 & None \\ C & 7 & A \\ D & 2 & A, B \\ E & 5 & C, D \\ F & 2.5 & D \\ G & 0.5 & E, F \\ \hline \end{tabular} Choose the correct project network diagram beiow. A. B. D. c. The critical activities are so they make up the critical path. The entire project will take days to complete. (Enter your response rounded to one decimal place.)