Question: begin{tabular}{|l|c|l|} hline Task & Duration & Dependencies hline A & 2 & hline B & 5 & A hline C & 3

\begin{tabular}{|l|c|l|} \hline Task & Duration & Dependencies \\ \hline A & 2 & \\ \hline B & 5 & A \\ \hline C & 3 & A \\ \hline D & 3 & A \\ \hline E & 1 & B \\ \hline F & 2 & C \\ \hline G & 3 & F,C \\ \hline H & 6 & E \\ \hline I & 3 & G \\ \hline J & 1 & I,H,D \\ \hline \end{tabular} Assume each activity in the above network diagram needs 2 workers per day to complete. Create a resource loading table that shows the number of workers needed for each day of the project. Next, discuss opportunities for resource levelling that may exist in the project. Be sure to be specific. Talk about which activities we might delay and whether it is possible to complete the project with fewer workers
Step by Step Solution