Question: begin{tabular}{lll} hline Activity & Immediate Predecessor hline A & & 5 B & A & 6 C & A & 2

\begin{tabular}{lll} \hline Activity & Immediate\begin{tabular}{lll} \hline Activity & Immediate

\begin{tabular}{lll} \hline Activity & Immediate Predecessor \\ \hline A & & 5 \\ B & A & 6 \\ C & A & 2 \\ D & B, C & 7 \\ E & B, C & 1 \\ \hline \end{tabular} For each of the following predecessor tables: - Draw a corresponding AON network. - Compute ES and EF for each activity. - Compute LS and LF for each activity. Find the critical path. - Determine the total slack and free slack