Question: Below are the data for a Time - Cost CPM scheduling model. Times are in days and costs include both direct and indirect costs. Activity

Below are the data for a Time-Cost CPM scheduling model. Times are in days
and costs include both direct and indirect costs.
Activity (A,B,C,D,E)
Immediate predecessor A is none. B is A. C is A. D is B and C. E is D.
Normal time for
A: 3
B: 4
C:4
D:3
E:2
Crash Time for
A: 2
B: 3
C:3
D:2
E:1
Normal cost (in dollars) for
A: 20
B: 30
C:20
D:50
E:50
Crash cost ( in dollars for)
A: 40
B: 45
C:35
D:60
E:55