Question: Question 2 Below are the data for a Time-Cost CPM scheduling model. Times are in days and costs include both direct and indirect costs. Immediate

Question 2 Below are the data for a Time-Cost CPM

Question 2 Below are the data for a Time-Cost CPM scheduling model. Times are in days and costs include both direct and indirect costs. Immediate predecessor None Crash Normal time time Normal cost (in dollars) Crash cost in dollars Activity 40 A NN Band C 60 a. Draw the project network. b. What is the total time for this project? c. What is the critical path? d. Which activity will you shorten in order to shorten this project by one day? Explain the reason for your choice