Question: Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect costs.
Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect costs.
| Immediate | Normal | Crash | |||
| Activity | Predecessor | Time | Time | Normal Cost | Crash Cost |
| A | None | 3 | 2 | $200 | $400 |
| B | A | 4 | 3 | $300 | $600 |
| C | A | 1 | 1 | $200 | $200 |
| D | B and C | 3 | 2 | $500 | $550 |
| E | D | 2 | 1 | $500 | $900 |
What is the total normal time of this project? and the total normal cost?
- Total time is 12 days, total cost is $1,500
- Total time is 12 days, total cost is $1,700
- Total time is 11 days, total cost is $1,600
- Total time is 13 days, total cost is $1,700
- Total time is 9 days, total cost is $1,700