Question: Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect
Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect costs. What are the total time of this project and total normal cost? Activity A B CDE Immediate Predecessor None A A B and C D Normal Time 3 4 1 3 2 Crash Normal Time Cost 2 $200 3 $300 1 $200 2 $500 1 $500 Crash Cost $400 $600 $200 $550 $900
Step by Step Solution
3.45 Rating (161 Votes )
There are 3 Steps involved in it
To determine the total time of the project using the normal time estimates we need to analyze the pr... View full answer