Question: Below given data on Normal time & cost , Crash time & cost for a project. Indirect cost of the Project is 1 0 0
Below given data on Normal time & cost Crash time & cost for a project.
Indirect cost of the Project is per day.
tableActhityPredecessor,tableDurationdzrstableCrashdurationtableNarmalcost of theactivitytableAdditionalcostdayto crash RBD Design, Deveiap, Document, Quality control, Launch,
a Oraw the Network Diagam R identify the critical path
b What is the normal project duratian & associgted cost?
c Find out total float for each actwity
Crash the above relevant activities srstematically and determine the optimum project time and cost fifef Tabie