Question: Below is a table of weekly demand and processing times in minutes at each machine for all of our products. Assuming there are 2 4

Below is a table of weekly demand and processing times in minutes at each machine for all of our products. Assuming there are 2400 minutes in each work week, how many minutes have we over planned production if we try to meet demand? (Round to the nearest minute, if we've under planned report 0).
Product Weekly Demand Time per unit at Machine 1 Time per unit at Machine 2 Time per unit at Machine 3 Time per unit at Machine 4
Cat hammocks 2219.08.66.70
Cat carriers 1454.109.20
Gift baskets (for Cats)22207.92.09.1