Question: Below is an activity network with times ( in weeks ) shown above each node: A 5 weeks leads to B 6 weeks and C
Below is an activity network with times in weeks shown above each node:
A weeks leads to B weeks and C weeks. B to d weeks. D to G weeks. C to E weeks. E to H weeks.
Which of the following statements is FALSE?
Multiple Choice
The critical path is ACEH
The earliest start time for Activity A is zero since it is the first activity.
The slack time Activity H is zero.
The latest start time of Activity H is weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock