Question: Below is an activity network with times (in weeks) shown above each node: Multiple Choice The critical path is A-C-E-H. The earliest start time for


Below is an activity network with times (in weeks) shown above each node: Multiple Choice The critical path is A-C-E-H. The earliest start time for Activity A is zero since it is the first activity. The slack time Activity H is zero. The latest start time of Activity H is 21 weeks