Question: Below is data for a project. (in months) What is the late start time for activity D? activity duration (months) predecessor A 1 -- B

Below is data for a project. (in months) What is the late start time for activity D? activity duration (months) predecessor A 1 -- B 5 A C 8 A D 3 A E 1 C F 6 B, C G 2 D, E H 4 F, G